• NOVEMBER - DECEMBER
  • JANUARY
  • FEBRUARY - MARCH
  • APRIL - MAY
  • JUNE - JULY
  • AUGUST

NOVEMBER - DECEMBER

The site is cleared and graded. All building foundations have been dug allowing the building pads to be formed. Concrete is being poured to create the foundations upon which the townhomes will be built.

JANUARY

Building pads are being poured as framing of the townhomes begins. In the next month all building pads will be poured and ready for framing.

FEBRUARY - MARCH

Framing of the townhomes is well underway. Roofs and windows are being installed to allow work on the interiors to being. Drywall installation and interior painting are underway. Interior tile and flooring installation begins.

APRIL - MAY

Interior work continues. Countertops, cabinets, appliances, light fixtures, and furniture are all being installed. Flooring is installed. Interior and exterior doors are installed. Front porch stoops are being poured along with exterior brick and siding completion.

JUNE - JULY

As the townhomes receive the finishing touches the project's amenities are underway. The leasing office, clubhouse, pool and fitness center are all finishing construction work as My House on 13th prepares for a successful grand opening. Landscaping is installed and manicured.

AUGUST

All construction work is complete and residents move in to their brand new townhome community.


© 2019-20. All rights reserved.
Handicapped Icon Fairhousing Icon Paw Icon
Plan 4 BEDROOM TOWNHOUSE SECOND FLOOR
Plan 4 BEDROOM TOWNHOUSE FIRST FLOOR
Plan 4 BEDROOM TOWNHOUSE GROUND FLOOR
Plan 5 BEDROOM TOWNHOUSE THIRD FLOOR
Plan 5 BEDROOM TOWNHOUSE SECOND FLOOR
Plan 5 BEDROOM TOWNHOUSE GROUND FLOOR
Plan 5 BEDROOM TOWNHOUSE THIRD FLOOR 13TH STREET
Plan 5 BEDROOM TOWNHOUSE SECOND FLOOR 13th STREET
Plan 5 BEDROOM TOWNHOUSE GROUND FLOOR 13th STREET